Traffic impact of future San Pedro bridge worries officials

Traffic impact of future San Pedro bridge worries officials

Construction for the project is expected to begin in the fall of 2025, impacting the neighborhoods of San Pedro and Wilmington, as well as the city of Long Beach.

Supervisor Janice Hahn speaks as LA County celebrated the grand reopening of Paramount Library, following a $4.8 million renovation in Paramount on Wednesday, July 17, 2024. The new design offer the residents a new seating, a community room with kitchenette, modern digital accessories, windows, and a living wall. (Photo by Brittany M. Solo Press-Telegram/SCNG)
Supervisor Janice Hahn  (Photo by Brittany M. Solo Press-Telegram/SCNG)

Los Angeles County Supervisor Janice Hahn is awaiting a response from Caltrans after sending the state agency a letter expressing her concerns over traffic impacts caused by a future bridge project in San Pedro.

Caltrans is in the process of finalizing the environmental planning phase of its Vincent Thomas Bridge Deck Replacement Project. The project aims to replace the entire bridge deck and its seismic sensors, and upgrade bridge railings, fences and median barrier.

Since April, the agency has held meetings for members of the public to comment on the project’s draft environmental impact report and environmental assessment, which ended early last week. Caltrans anticipates the release of this document in the fall, which will outline a selected alternative chosen for construction and identify detour routes. A motorist information plan will be developed soon after as well.

Construction for the project is expected to begin in the fall of 2025, impacting the neighborhoods of San Pedro and Wilmington, as well as the city of Long Beach.

While the project still has some ways to go, Supervisor Hahn — who represents the Harbor Area and Long Beach — is urging Caltrans to work with cities up and down the I-110 and I-710 freeways to develop clear communication and a plan that re-routes commuters and goods movement well in advance of the bridge project.

In her letter sent Wednesday, Hahn said she wants to minimize disruptions in the port communities that already “bear the brunt of poor air quality and damaged roads because of their proximity to these goods movement centers.”

“The project will have huge impacts for tens of thousands of commuters who use this bridge everyday, and it will severely disrupt goods movement around the ports for years,” Hahn said in her letter. “No matter which construction timeline Caltrans adopts, the communities impacted by this project need to be fully engaged and have their concerns addressed thoroughly before any road closures begin.”

Eric Menjivar, media relations manager for Caltrans District 7, which oversees the highways and freeways in the Southland, confirmed the agency received Hahn’s letter and will respond.

“Caltrans understands the impacts the Vincent Thomas Bridge Deck Replacement Project will have on residents, businesses, motorists and the ports, which is why the department will remain eager to engage our partners in the environmental process and prior to construction. Caltrans is committed to keeping the stakeholders of San Pedro, Wilmington, Long Beach, the South Bay and Harbor/Gateway communities informed of progress on the project and the anticipated impacts before construction begins,” Menjivar said in an email to City News Service.

Menjivar noted that Caltrans does plan to hold public meetings in the future with the community to inform them about the project.Caltrans is considering four construction options with the “single-stage construction” being a top contender because it could be done in as little as 16 months with detours and 24/7 work.

The Vincent Thomas Bridge is in need of deck replacement because it was built in 1963 and has been in service for 60 years. The agency says the bridge is “structurally sound” but the bridge deck is “rapidly deteriorating,” caused by heavy traffic loading, as well as environmental deterioration due to age and being close to the sea.

The opening of a new training center at the Port of Los Angeles to provide longshoreworkers with the skills needed to expand into cargo-handling maintenance and repair took place Friday May 31, 2024. The new $16.4 million facility is located on a four-acre parcel adjacent to Pier 400 in San Pedro. The 20,000 square foot training center includes classroom space and on-the-job training areas which include heavy equipment such as forklifts, column lifts, welding stations, a jib crane, and truck chassis. Los Angeles City Council member Tim McOsker gives remarks during the event. (Photo by Chuck Bennett, Contributing Photographer)
Los Angeles City Council member Tim McOsker  (Photo by Chuck Bennett, Contributing Photographer)

Los Angeles City Councilman Tim McOsker, who represents the 15th Council District, which encompasses the Harbor communities, has also expressed similar concerns. McOsker nicknamed this possible traffic scenario as “Harborgeddon” — alluding to the city’s “Carmageddon” in 2011 when Caltrans closed the I-405 for two weekends for a bridge reconstruction project.

In a communications sent to Caltrans on July 15, McOsker recommended the state agency undertake similar measures done in 2011 to inform commuters —including print, radio, online ads and email blasts to more than 6,000 organizations. Electric billboards were also configured to broadcast messages about the impending closure weeks before.

The councilman believes the bridge project will have even more challenges as it will take about 16 months to complete. McOsker also urged for a robust public safety plan, including the deployment of more crossing guards near schools and assistance from the California Highway Patrol.

McOsker hopes the project can be completed in less time than the estimated 16 months, if the agency opts for the “single-stage construction,” because there may be potential overlap with the 2028 Summer Olympics in Los Angeles. The city of Long Beach will also host several events at its stadiums and beachfront.